The construction photos below were taken between March 1995 and April 2002. Occupancy began in January 1999.














.:: Site work
.:: Pouring the slab
.:: Adobe walls
.:: Roof framing
.:: Roof/Ceiling Details
.:: Exterior view
.:: Interior view
.:: Aerial view

Site work, stem walls and underground utilities.

Bill Galagher and Professor Scheatzle at site in AUgust 1995. Site cleared and ready for footings.
 
Completed stem walls - October 1995.

Routing of buried electrical, water, radiant system supply and return, and drainage -December 1995. Ready for slab rebar - January 1996.

Ready for slab rebar. Stub ups for radiant
system, plumbing and drainage -December 1995.
[back to top]

Placing the radiant floor tubes and pouring the slab

Radiant floor tubes attached to rebar in living room/dining room area - January 1996. Pouring the slab, showing floor manifold for the center zone
 
Slab pour finished - January 1996

Adobe Walls

Delivery of adobe blocks-January 1996. Start of adobe walls showing window forms -January 1996
   
Placing lentils in south wall-January 1996 Forming bond beams on top of adobe walls-February 1996
   
View of bond beam from the top-March 1996 Framing above bond beams-March 1996
 

Roof Framing

Beginning the roof framing-March 1996 Roof framing progress looking southwest- 1996
   
Roof framing showing detail of ridge beam
and rafters- 1996
Roof framing nearing completion- 1996
 

Roof/Ceiling Construction Details

Section through roof/ceiling assembly showing various components Applying radiant barrier in rafter air space-January 1997
   
Looking into rafter air space showing radiant barrier, 2 inch air space below and 8 inch fiberglass batt insulation- 1997 Beginning to apply Styrofoam board insulation over vapor barrier at bottom of rafters. This prevents water vapor from the outside from reaching the cold capillary tubes and condensing.- 1997
   
Styrofoam board insulation over vapor barrier at bottom of rafters. This prevents water vapor from the outside from reaching the cold capillary tubes and condensing.- 1997 Roof ridge venting before cap is applied.- 1997
   
 
Roof ridge venting with screen in place before top cap is applied.- 1997

Exterior Work

 
Installing windows.- 1998

Interior Work

 
Flagstone floor completed.- 1998

Aerial view  
[back to top]





Carefree House


Objective

Project Description

Construction Photos


Data

Performance

Animation

Environmental control

Simulation

Conclusions & Observations


Future Work

Acknowledgements


References


Atascadero


























































































 


Copyright © Arizona Board of Regents 2002 | ASU Privacy Statement